Health and Safety
DSP 2000 Ltd provide our clients with full Health and Safety
advice and act as independent CDM Co-ordinators in accordance with
the Construction [Design and Management] Regulations 2007.
We advice and assist our clients in their role and duties when
undertaking any construction work, and as CDM Co-ordinators we
will:
- Notify details of the project to HSE.
- Co-ordinate health and safety aspects of design work and
co-operate with others involved with the project.
- Facilitate good communication between the client, designers and
contractors.
- Assist the client to collect and pass on pre-construction
information to all parties
- Liaise with the principal contractor regarding ongoing design
work.
- Ensure that the construction phase plan is adequate for the
wok
- Prepare or update the health and safety file.
- On projects that last less than 30 days or involve less than
500 person days of construction work then DSP 2000 Ltd will offer
appropriate services to advise the Client of their duties
Additionally as CDM Co-ordinators we liaise with designers and
principal contractors to:
- Ensure where practical that hazards and risks are eliminated
during design.
- Ensure that any remaining risks are identified.
- Obtain from the designer and contractor information for the
health and safety file
- Inspect the site to ensure that the construction phase plan is
being adequately managed and updated
|
|
Steeple House
Percy Street
Coventry
CV1 3BY
Tel: 024 7652 0866
Fax: 024 7652 5040
|

|

|

|
|